North Street / Field study 001

From flight.
To field.
To the inch.

A field validation study using aerial reconstruction and ground measurements at a real residential site. Seven MipMap readings, checked against tape and laser measurements on the ground.

Watch the film ↓See the comparison
North Street MipMap reconstruction with measurement annotations
234 source photos · MipMap 3D model. The earlier front-wall annotation was revised to 40.00 ft after matching the field endpoints.
7features checked
5 / 7within one inch of field references
0.1–2.2 inabsolute differences, rounded
No rescalingusing the field measurements

The site in motion

Measurements, in place.

A smooth 13-second orbit with tracked measurement overlays on the house, front lumber and box board, and dumpster.

Tape and laser field-reference measurements shown in feet and inches over the Gaussian splat. These are tracked visual overlays, not new measurements from the video. Compare the field references with the MipMap model readings in the table below. Watch video ↗

01 / Measurement check

The numbers, side by side.

The field measurements are the reference. Signed differences show how far the displayed MipMap reading falls above or below that reference.

Feature Field reference MipMap model Difference Relative difference
House front length 40′ 2″ · Tape 40.00 ft −2.00 in −0.41%
House width 32′ 1″ · Tape 32.02 ft −0.76 in −0.20%
Driveway 24′ 6″ · Tape 24.46 ft −0.48 in −0.16%
Dumpster length 267 11/16″ · Laser 22.23 ft −0.93 in −0.35%
Dumpster width 89.5″ · Tape 7.45 ft −0.10 in −0.11%
Lumber 144″ · Tape 12.18 ft +2.16 in +1.50%
Box 96″ · Tape 8.06 ft +0.72 in +0.75%

− Shorter than the reference · + Longer than the reference. Calculated from rounded on-screen readings.

Mean absolute difference across these seven selected checks: approximately 1.02 inches.

Five features were within one inch of their field references. The front wall differed by 2.00 inches; the lumber by 2.16 inches. This is a comparison of seven features, not a site-wide accuracy certification.

02 / On the ground

Real measurements.
Recorded on site.

Tape stretched along the house exterior wall

Match the endpoints.

The front reading was revised to 40.00 ft after the endpoints were moved to match the tape placement, just above the exposed foundation.
Bosch laser with selected lower reading of 267 and 11/16 inches

A laser reference.

The selected 267 11/16-in laser reading replaces the initial rounded 267-in dumpster reference.
Tape at the wooden box endpoint near 96 inches

Check the small details.

The field length is 96 in. The model reading is 8.06 ft, approximately +0.72 in.

03 / Spatial context

Walk around the evidence.

Explore the North Street Gaussian splat. This scene provides visual context; the results above come from the MipMap 3D model.

Explore the interactive 3D scene — approximately 103 MB

Open full SuperSplat viewer ↗

04 / Study notes

Measured with care.
Reported with context.

One reconstruction for the results

MipMap Desktop 3.2.3 · Ultra High · 234 photos. Source task: north st-20260906. Earlier WebODM checks are separate and are not included in this table.

Independent field references

Tape and laser measurements were used for comparison, not to rescale the model. Front-wall endpoint placement was corrected to match the field measurement.

Know what the comparison measures

Results use rounded on-screen US-foot readings. Unit-conversion differences are negligible at the reported precision. Full endpoint correspondence and horizontal-versus-3D distance mode remain to be verified for every feature.

A focused field check

These results describe agreement for seven selected features. They do not establish absolute geospatial accuracy, repeatability, or accuracy throughout the reconstruction.

05 / Project deliverables

What a municipality/project team receives

  • Georeferenced orthophoto/site overview
  • Recurring aerial progress imagery
  • Annotated dimensional references
  • Point-cloud or 3D model deliverables
  • Gaussian-splat visualization where useful
  • Organized image archive by date/location
  • Comparison measurements and field-reference notes
  • Stakeholder-ready PDF summary
  • GIS-compatible outputs when appropriate
  • Repeat capture from defined viewpoints

Deliverables are scoped according to project requirements, coordinate-control needs, and the intended use of the data.

06 / Public-sector & infrastructure applications

Documentation for project teams.

Applications include construction progress, existing-condition documentation, facility/site records, asset documentation, planning reference, visual inspections, recurring project monitoring, and stakeholder communications.